Informacja

Drogi użytkowniku, aplikacja do prawidłowego działania wymaga obsługi JavaScript. Proszę włącz obsługę JavaScript w Twojej przeglądarce.

Tytuł pozycji:

A genetic algorithm and B&B algorithm for integrated production scheduling, preventiveand corrective maintenance to save energy

Tytuł:
A genetic algorithm and B&B algorithm for integrated production scheduling, preventiveand corrective maintenance to save energy
Autorzy:
Sadiqi, Assia
El Abbassi, Ikram
El Barkany, Abdellah
Darcherif, Moumen
El Biyaali, Ahmed
Data publikacji:
2020
Wydawca:
Polska Akademia Nauk. Czytelnia Czasopism PAN
Tematy:
scheduling
maintenance
genetic algorithm
branch
bound
MILP
modeling
optimization
CPLEX
Python
Źródło:
Management and Production Engineering Review; 2020, 11, 4; 138-148
2080-8208
2082-1344
Język:
angielski
Prawa:
Wszystkie prawa zastrzeżone. Swoboda użytkownika ograniczona do ustawowego zakresu dozwolonego użytku
Dostawca treści:
Biblioteka Nauki
Artykuł
  Przejdź do źródła  Link otwiera się w nowym oknie
The rapid global economic development of the world economy depends on the availability of substantial energy and resources, which is why in recent years a large share of non-renewable energy resources has attracted interest in energy control. In addition, inappropriate use of energy resources raises the serious problem of inadequate emissions of greenhouse effect gases, with major impact on the environment and climate. On the other hand, it is important to ensure efficient energy consumption in order to stimulate economic development and preserve the environment. As scheduling conflicts in the different workshops are closely associated with energy consumption. However, we find in the literature only a brief work strictly focused on two directions of research: the scheduling with PM and the scheduling with energy. Moreover, our objective is to combine both aspects and directions of in-depth research in a single machine. In this context, this article addresses the problem of integrated scheduling of production, preventive maintenance (PM) and corrective maintenance (CM) jobs in a single machine. The objective of this article is to minimize total energy consumption under the constraints of system robustness and stability. A common model for the integration of preventive maintenance (PM) in production scheduling is proposed, where the sequence of production tasks, as well as the preventive maintenance (PM) periods and the expected times for completion of the tasks are established simultaneously; this makes the theory put into practice more efficient. On the basis of the exact Branch and Bound method integrated on the CPLEX solver and the genetic algorithm (GA) solved in the Python software, the performance of the proposed integer binary mixed programming model is tested and evaluated. Indeed, after numerically experimenting with various parameters of the problem, the B&B algorithm works relatively satisfactorily and provides accurate results compared to the GA algorithm. A comparative study of the results proved that the model developed was sufficiently efficient.

Ta witryna wykorzystuje pliki cookies do przechowywania informacji na Twoim komputerze. Pliki cookies stosujemy w celu świadczenia usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Twoim komputerze. W każdym momencie możesz dokonać zmiany ustawień dotyczących cookies

Prześlij opinię

Twoje opinie są dla nas bardzo ważne i mogą być niezwykle pomocne w pokazaniu nam, gdzie możemy dokonać ulepszeń. Bylibyśmy bardzo wdzięczni za poświęcenie kilku chwil na wypełnienie krótkiego formularza.

Formularz